Ambigous Question
Submitted by elthox on Fri, 07/19/2013 - 16:05
| You are the project manager in an aircraft manufacturing company developing a new range of supersonic fighter planes. Since government approval and involvement are essential, you hire a lobbying firm to get government support to prevent unnecessary changes in your project. Which process is this an example of? |
||
| Choice 1 | Perform Integrated Change Control | |
| Choice 2 | Risk Management | |
| Choice 3 | Cost Management Plan | |
| Choice 4 | Develop Project Management Plan | |
Forums:


pmpnewster
Fri, 07/19/2013 - 16:11
Permalink
Choice 2 Risk Management
Regards.
elthox
Fri, 07/19/2013 - 16:20
Permalink
Me too selected 2.
Me too selected 2.
th9063
Fri, 07/19/2013 - 16:52
Permalink
1
1
vikula01
Fri, 07/19/2013 - 16:56
Permalink
choice 2
The lobbying firm is not the gate keeper of changes - They are hired by us to work with government to prevent the changes ( risk ) - which is a risk management plan .
elthox
Fri, 07/19/2013 - 17:26
Permalink
As per test authors, the
As per test authors, the right answer is Choice 1
ginumon
Fri, 07/19/2013 - 18:40
Permalink
Preventing change is part of PICC
Hence the answer is 1