Need Help

Resource leveling will often affect the project by making it:

A.
Shorter.

B.
More responsive to customer needs.

C.
Longer and more responsive to customer needs.

D.
Shorter and more responsive to customer needs

E.
Longer

E. Longer

thank you .

but why ???

the idea of resource leveling is to decrease schedule not to make it longer

Resource leveling will put cap on how many resource you can use each day/week/month. For example, you plan 8 recourses in first week and 5 in next week and so forth. Now you have to use 5 6 resources through out. It will take longer time to get same work.