Question from Scordo - Cost of loans on the project

 Hello guys ,

for some reasons my account was blocked yesterday when i was posting this question , no idea why

anyway..

A major construction project has included in the project budget the cost of the construction loans taken out to finance the work, and this will be accounted for on a monthly basis. The project manager will factor in these cost estimates into the project during which process?

A. Estimate Project Cost

B. Estimate Activity Resources

C. Estimate Activity Durations

D. Estimate Activity Costs

For me i would say D but the answer was C

if you look closely. Only C. Estimate Activity Durations is valid process . Its "Esimate Costs" not Estimate Activity Costs

 Oh, True

Thanks