Need to understand abt control account
Submitted by Rashmi dr on Mon, 06/17/2013 - 06:19
Kindly my frnds,
Need more information abt control account.. not abe ubderstand with given meaning words in Head First...........
Help me out,
Reg,
Rashu
Forums:


cnppmp
Mon, 06/17/2013 - 10:38
Permalink
Control account creation in
Control account creation in final stage of WBS finalization.
Each control account can have one or more work packages assigned but multiple control accounts cannot be assigned to one Work package.
It is unique identifier, the financial maangement team uses the control account for control and reporting purpose. The scope, cost and schedule information are intergrated & tracked through the control account and EV reproting is done through control account.
WBS component used for project cost accounting
In the cost aggregation the highest level aggretaion is at Control account level, the next is cost baseline creation with contingency reserve adding to the aggregated cost.
Regards
CN Patil
sanskrit
Mon, 06/17/2013 - 12:47
Permalink
Nice write-up cnppmp
Nice write-up cnppmp.
MANOJ RAMRAOJI ...
Mon, 06/17/2013 - 16:41
Permalink
In WBS hierarchy the CA
In WBS hierarchy the CA (ControlAccount) is usd for management purpose, it is the point at which performace of schedule and cost is measured.