Estimate complete calculation
Greetings,
came across this question and wanted to know the correct method of calcuation to get the answer - not sure of answer though - sorry
Project exploration - team has to reach XYZ.
TASK DURATION
Transportation to xyz 20days
food and equiment 5days
staff 10days
task1 5days
travelling 200km at 10km/day speed 20days
task2 0days
the constraint is task1 , food & equiment, staff has to start at same time
halfway through the project due to storm the speed is reduced by 25%
how many days will team take to reach XYZ.
Appreciate your response.


ssundar
Wed, 06/05/2013 - 15:59
Permalink
Longest path is the project
Longest path is the project duration. So, even 3 tasks reduced by 25%, the longest duration would be 20days.
MANOJ RAMRAOJI ...
Wed, 06/05/2013 - 16:33
Permalink
26.66 Days
In normal case distrace travelled is 10KM/day, due to strom constraints now their speed is 7.5KM/Day.
Hence to cover 200 KM they will be required 26.66 Days
Regards,
Manoj
piggyfox
Thu, 06/06/2013 - 08:02
Permalink
@Manoj - it says halfway
@Manoj - it says halfway through the speed resduced hence can we assume its to cover another 100km with speed of 7.5km/day it takes 13 days??
BK
Wed, 06/05/2013 - 16:41
Permalink
May I know the source
May I know the source please?
piggyfox
Thu, 06/06/2013 - 07:59
Permalink
this was a pmp actual exam
this was a pmp actual exam question