LS and LF question from pmzilla
Activity X has an FS relationship with a 1-day lag with succeeding Activity Y. Activity X also has a SS relationship with a 5-day lag with succeeding Activity Z. Assume that Activity X has no other immediate succeeding relationships. Given the following: Activity Y: Late Start is Day 11; Late Finish is Day 15 Activity Z: Late Start is Day 11; Late Finish is Day 15 Activity X: Duration is 5 days. Calculate Activity X's Late Start and Finish dates.( Assume: Duration = finish date minus start date + 1)
Can someone please explain the logic behind this?
A:Late Start is Day 5; Late Finish is Day 9.
B:Late Start is Day 6; Late Finish is Day 11.
C:Late Start is Day 6; Late Finish is Day 10.
D:Late Start is Day 5; Late Finish is Day 11.
Correct answer is A.But I think it would be B.Any suggestions pls?


mirrar
Mon, 03/30/2009 - 09:26
Permalink
May you please explain how
May you please explain how you got answer B?
Answer B will give Activity X a duration of 6... (11-6+1)
So the answer should be either A or C.
My logic is:
Since Activity X and Activity Y are having FS relationship with a lag of 1 day, that means the Late Finish of Activity X has to be 9. (If there is no 1 day lag, then LF of Activity X would be 10). This makes A the only answer.
crabapple
Mon, 03/30/2009 - 12:40
Permalink
When you perform a backward
When you perform a backward pass for the activity X, LF has to be 11 ..?
Since, Activity X's LF will Activity Y's and Activity Z's LS.
I am following the solution per Rita book.
My solution was B as well.
-crabs
jenshrimp
Tue, 04/07/2009 - 21:27
Permalink
When you perform a backward
The S-S Relationship means that Z cannot start until X has Started (+ 5 Days of Lag). It does not mean that Z starts immediately after X starts + 5 days or concurrently with X + 5 days.
mirrar
Wed, 04/08/2009 - 02:15
Permalink
I guess I found the key to
I guess I found the key to this question now.
Both answer A and B can be correct, as there are two methods of finding LS/LF/ES/EF:
1. Rita's method:
Duration=EF-ES or LF-LS, successor ES (or LS)=predecessor EF (or LF)
2. Non-Rita method:
Duration=EF-ES+1 or LF-LS+1, successor ES (or LS)=predecessor EF (or LF)+1
However, since the question has stated an assumption: Duration = Finish date - Start Date + 1, non-Rita method is to be used. Hence A is the correct answer for this question.