Stakeholder Identification Levels
Submitted by farrous13 on Sun, 06/02/2013 - 22:04
Hello guys,
Could you help me understand the answer to this question:
What BEST describes stakeholders indentification levels?
A: Interest, expectations, importance and influence.
B: Interest, power, importance and influence
C: Impact, power, importance and influence
D: Impact, expectations, importance and interest.
The Answer is A. But I answered C. BUT for me all are right
Forums:


vijayavadrevu
Mon, 06/03/2013 - 03:06
Permalink
As per PMBoK, the four
As per PMBoK, the four facttors are
power (level of authority)
interest (level of concern)
influence (active involvement)
impact (ability to affect changes)
Looking at the options given, I think option B is right
Interest, power, importance and influence assuming that importance is same as impact i.e., ability to affect changes
this is my understanding
san
Mon, 06/03/2013 - 05:33
Permalink
This should be A. Refer PMBOK
This should be A. Refer PMBOK 246 (10.1 section)
vijayavadrevu
Mon, 06/03/2013 - 06:05
Permalink
@farrous13As stated by @san ,
@farrous13
As stated by @san , option A is available in PMBoK and looks like the right option. Can you please confirm the answer?
th9063
Sun, 07/21/2013 - 03:24
Permalink
pmbok pg 246 2nd paragraph
pmbok pg 246 2nd paragraph