A Risk Question
Submitted by Jgrind07 on Fri, 05/24/2013 - 20:18
The Risk Management plan will usually contain the definitions of risk probability and impact. Which of the following has the highest impact (negative) on a project?
-
A rating of 1.1 on the impact scale
-
A rating of 0.8 on the impact scale
-
A rating of 0 on the impact scale
-
A rating of 0.1 on the impact scale
Forums:


Geethika
Fri, 05/24/2013 - 21:18
Permalink
B
Impact being measured in the range 0 to 1, 0.8 has highest impact on project.
sanskrit
Fri, 05/24/2013 - 21:36
Permalink
B
B
Jgrind07
Sat, 05/25/2013 - 01:20
Permalink
Thanks Geethika,Yes, the
Thanks Geethika,
Yes, the impact is measured between 0 to 1 but I do not see reference in PMBOK. I came to know the answer only after authors explaination.
Thanks
Jai
vijayavadrevu
Sat, 05/25/2013 - 03:00
Permalink
You can also refer the link
You can also refer the link below:
http://pmi.books24x7.com/assetviewer.aspx?bookid=32020&chunkid=500277527
which speaks about risk impact scale
Regards
Vijaya
Jgrind07
Sat, 05/25/2013 - 03:57
Permalink
Excellent! Tanks, VijayaJai
Excellent! Tanks, Vijaya
Jai
jvleminc
Wed, 05/29/2013 - 16:07
Permalink
B
Keyword is risk *scale*, indicating a 0-1 range.