role of stakeholder
Submitted by vijayavadrevu on Fri, 05/17/2013 - 20:05
Who determines the role of each stakeholder
A)The stakeholder and the sponsor
B)The project manager and the stakeholder
C)The team and the project manager
D)The project manager and the sponsor
Forums:


crushPMP
Fri, 05/17/2013 - 20:07
Permalink
B?
B?
vijayavadrevu
Fri, 05/17/2013 - 20:14
Permalink
Yes it should be B but the
Yes it should be B but the answer is given as D. Hence confused
eng_mut
Sat, 05/18/2013 - 10:06
Permalink
it is B regarding to rita page 308
it is B regarding to rita page 308
vijayavadrevu
Sat, 05/18/2013 - 10:50
Permalink
Yes, Thank You
Yes, Thank You
cnppmp
Sat, 05/18/2013 - 11:50
Permalink
C
It is C right?
Regards
CN Patil
vijayavadrevu
Sat, 05/18/2013 - 14:39
Permalink
No, it is B. Refer RITA' s
No, it is B. Refer RITA' s book page 304