impact of stakeholders
Submitted by vijayavadrevu on Fri, 05/17/2013 - 19:48
By identifying the potential impact of stakeholders, the project manager is intending to
A)Plan Communication
B)Define scope
C)Analyze stakeholder
D)Identify constrains
Forums:


Jgrind07
Fri, 05/17/2013 - 23:34
Permalink
C. Analyze stakeholder
C. Analyze stakeholder
BK
Sat, 05/18/2013 - 07:33
Permalink
c
c
rwmv
Sat, 05/18/2013 - 09:29
Permalink
CPI
C
vijayavadrevu
Sat, 05/18/2013 - 10:11
Permalink
Yes, C is right
Yes, C is right