chg qn

 Your team has recommended a change to the Verify Scope process. What’s the first thing you should do?



 

 

a.Implement the change.

b.Analyze the change versus the Project Management plan to see what its impact will be.

c. Write up a change request.

d.Tell your team that the process has already been decided and they should follow it

crushPMP's picture

 B?

No question marks on B. 

It is B.

Team analysis need to be analyzed on performance measurement base to understand impacts

 

 Yes, B is Correct Ans.