Planning/Time Management Process Q

crushPMP's picture

 

32. 

Which of the following activities fall under the planning process group but not under the project time management?

  1. Estimating the type of materials and equipment needed to perform project activities

  2. Formalizing the acceptance of completed deliverables

  3. Identification of various activities to produce the project deliverables

  4. Developing a detailed description of the project and product being developed

B

c

 C

 D as that is define scope.

A : Estimate Activity Resource : Time Management and Planning

B : Verfy Scope : Integration Management and M&C

C : Define Activities : Time Management and Planning

D : Define Scope : Scope Management and Planning

Answer is D.

 

A : Estimate Activity Resource : Time Management and Planning

B : Verfy Scope : Scope Management and M&C

C : Define Activities : Time Management and Planning

D : Define Scope : Scope Management and Planning

crushPMP's picture

 Correct Ans is D

cnppmp's picture

D refers to project scope definition, so it is pertaining to planning but not to Time management..rest of them belong to Time management and Execution.


 


Regards


CN patil