EMV Question
Submitted by san on Wed, 05/15/2013 - 12:45
As part of Quantitative Risk Analysis, a project manager has derived four packages with the following probability and impact. Using EMV (Expected Monetary Value) which one should he use in the project?
A) Work package I : Probability 15 % & Impact $ 20,000
B)Work package II: Probability 7 % & Impact $ 10,000
C) Work package III: Probability 7 % & Impact $ 15,000
D)Work package IV: Probability 15 % & Impact $ 10,000
Forums:


rwmv
Wed, 05/15/2013 - 12:53
Permalink
Ans-A
Answer-A
crushPMP
Wed, 05/15/2013 - 12:55
Permalink
A
A
Jgrind07
Wed, 05/15/2013 - 15:37
Permalink
A
A
y0zh
Wed, 05/15/2013 - 19:23
Permalink
Impact can be either positive
Impact can be either positive or negative. Since this impact is positive, its some e.g. Profit, cost saving. Thus the bigger PxI the better
cnppmp
Thu, 05/16/2013 - 09:49
Permalink
A
3000 is for A so it is biggest and so choose it, sicne it is positive 3000.
Regards
CN Patil
BK
Thu, 05/16/2013 - 10:26
Permalink
I am bit confused here.
I am bit confused here.
Higher P X I value signifies higher risk (Can be threat or opportunity), then why we go with option 1?
then the option should be B, the lowest value/lowest risk.
@san,
what is the clarification/ans given by the provider?
sspawar
Thu, 05/16/2013 - 12:12
Permalink
here amount shown as
here amount shown as positive value hence it is opportunity aand higher one is A
san
Thu, 05/16/2013 - 12:18
Permalink
Explanation:Answer (b) Work
Explanation:
Answer (b) Work package II: Probability 7 % & Impact $ 10,000 with EMV of $700 has the lowest value. EMV(Expected Monetary Value )= Probability * Impact. Lower the ExpectedMonetary Value (EMV), lower is the risk involved in the work package.
I am confused between A and B. Please clarify..
Thanks