Help with ETC and EAC
Submitted by mlmPMP2013 on Mon, 05/13/2013 - 23:02
Hi All --, could you please help me understanding this question:
When is the EAC forecast for ETC work considering both SPI and CPI factors most useful?
The correct answer is #1, for the following reason: The EAC forecast for ETC work considering both SPI and CPI factors is most useful when the project schedule is a factor impacting the ETC effort.
I don't understand how SPI and CPI factor into ETC effort?
Forums:


rwmv
Tue, 05/14/2013 - 01:14
Permalink
#1 for sure
Answer=1
SPI= EV/PV-- schedule performance Index is very important indicator for ETC. If you have a schedule variance, your ETC will be off.
pmpnewster
Tue, 05/14/2013 - 01:42
Permalink
Why not #3? EAC is what we
Why not #3? EAC is what we compute initially... and then obtain ETC from it. AC is water gone under the bridge.