Q. Cost question

 You’ve consulted your Earned Value calculations to find out the EAC and ETC of your project. Which of the following is the BEST place to put that information?

A. Work performance information

B. Forecasts

C. Quality control measurements

D. Lessons learned

 
crushPMP's picture

 A. WPI?

The EAC and ETC are referred to the Forecasts.


Regards


CN Patil

Insteat of typing B I typed C, actually I meant B Forecast

 B. Forecasts

 Forecasts

B. Forecast