What does it mean, when they say Critical Path method uses deterministc method, meaning it uses one time estimate?

admin's picture

The time required to complete each activity can be estimated using past experience or the estimates of knowledgeable persons. CPM is a deterministic model that does not take into account,  variation in the completion time, so only one number is used for an activity's time estimate