Est schedule Qn
Submitted by BK on Wed, 05/08/2013 - 12:08
|
In your project, you are estimating schedule activity costs by determining the unit cost rates, e.g., staff costs per hour. All the following could be used to determine resource cost rates EXCEPT: |
||
|
|
||
|
1 |
Statistical relationship between historical data and other variables |
|
|
|
||
|
2 |
Gathering quotes |
|
|
|
||
|
3 |
Standard rates with escalation factors (for contracts) |
|
|
|
||
|
4 |
Commercial databases or seller published price lists |
|


rwmv
Wed, 05/08/2013 - 12:43
Permalink
option 4
ans=4
sspawar
Thu, 05/09/2013 - 03:15
Permalink
IN my opinion it should be
IN my opinion it should be 2.
Gathering quotes ---- it is an artivity during, conduct procurement, against (in response of) RFQ.
crushPMP
Thu, 05/09/2013 - 03:16
Permalink
2. Gathering Quotes?
2. Gathering Quotes?
bkthakkar
Thu, 05/09/2013 - 04:31
Permalink
While gathering quotes, we
While gathering quotes, we can ask for the detailed analysis whereas in case of unit rates but incase of commercial databases, it does not provide you the break up.
Hence I would go for answer 4
Bhavesh
sspawar
Thu, 05/09/2013 - 05:44
Permalink
dear bktwhen u will define
dear bkt
when u will define resource cost , ( I think never after calling quotation)
in option D - also seller price list is given,
Database may be of price list
BK
Thu, 05/09/2013 - 06:13
Permalink
Ans Given as 1.Parametric
Ans Given as 1.
Parametric estimating uses a statistical relationship between historical data and other variables.
All the other options are valid ways to determine unit cost rates.