Critical resource's time?
Submitted by crushPMP on Thu, 05/09/2013 - 03:04
Very critical resource is on another team. It is very important that you get his time for your project. You have contacted his team's manager multiple times, but have received a poor response. What should you consider doing next?
A. Plan for alternate resource since this resource is not available
B. Try to use management influence to obtain the resource's time
C. Contact the manager once again to see if he can help
D. Train another resource within your project
Forums:


sspawar
Thu, 05/09/2013 - 04:03
Permalink
Bbks A and D are similar,
B
bks A and D are similar, and C you have done several times.
rwmv
Thu, 05/09/2013 - 05:50
Permalink
I would go with OPTION B
I would go with OPTION B
BK
Thu, 05/09/2013 - 06:13
Permalink
Goin with B
Goin with B
crushPMP
Thu, 05/09/2013 - 14:58
Permalink
Ans is B, but I still don't
Ans is B, but I still don't get it that you would have to use "influence" to get your work done...
Jgrind07
Thu, 05/09/2013 - 15:42
Permalink
It is PMIsm. Please refer the
It is PMIsm. Please refer the Acquire Project Team process and it says, The PM or PM team should effectively negotiate and influence others who are in a position to provide required human resources for the project. (Pgae 225)
Thanks
Jai