cost estimates - include indirect costs?

crushPMP's picture

While managing a large project, the project manager decided to include indirect costs as a part of his cost estimate. If indirect costs are included in an estimate which of the following is true?

A. Indirect costs should be included at the activity level or higher

B. Indirect costs should be included at the activity level or lower

C. Indirect costs should only be included in earned value measurements and not in cost estimate.

D. Indirect costs should not be included in cost estimates

 As I understand, option A is correct one.

Indirect cost is taken as % age of direct cost, and while aggregation of estimate costs, of various activities, in process of determining budget/ baseline cost , it is added as an activity cost estimate. 

It is considered as a seperate ativity or WPkg or Control Account cost estimate, 

 I would go with A. If its a large project indirect costs should be added at the activity level

 

 

 Answer A

 PMBOK page no.174. first para. last sentence

 

"Indirect costs, if they are included in the project estimate, can be included at the activity level or at higher levels."

 

crushPMP's picture

^ Thanks for the reference, abdsal!