Question: A Cost Management Plan contains a description of what?

a) The project cost
b) How resources are allocated
c) The budgets and how they were calculated
d) The WBS level at which earned value will be calculated

Right answer is D.

It is not answer C because the Cost management plan might have the methodology used to create the budget, but it won't contain the budget.

The answer to the question suggests that Management Plans always only contain the "management methodology and principles", but never the outputs.

So for example Cost baseline, Risk Matrix, Procurement documents, Ressources Calendar, etc... should  NOT be in the Project Mangement Plan / subsidiary Plans. Is it correct ?

Thanks a lot for clarifications.

 

 

 Yes cost baseline is a plan, which possesses the budgets.

and it is output of cost management plan .

cost management plan as stated - how to carry out / work out / act , but not how was done/ was calculated/etc-etc.