Which relation is most correct?
Submitted by sspawar on Fri, 05/03/2013 - 09:51
Which relation is most correct?
A. BAC-(EV/CPI) = (BAC-EV)/TCPI
B. BAC-(AC/CPI) = (BAC-EV)/TCPI
C. BAC-EV = (BAC-EV)/CPI
D. BAC = EV1/CPI1 + EV2/CPI2
Forums:


san
Fri, 05/03/2013 - 10:35
Permalink
Option could be A.LHS side
Option could be A.
LHS side =BAC -(EV/ CPI)= BAC-(EV*AC) / EV= BAC -AC
RHS side =(BAC-EV)/TCPI = (BAC-EV)(BAC-AC)/(BAC-EV) = BAC-AC (Considered TCPI based on BAC)
Please correct me , if I am wrong.
Thanks
sspawar
Fri, 05/03/2013 - 10:49
Permalink
Yes You are absolutely
Yes
You are absolutely correct.
Have you seen last q at page 4 of topic - Q framed by me?
san
Fri, 05/03/2013 - 10:57
Permalink
Thank you sir for the
Thank you sir for the confirmation.Till now, I have not gone through those questions. I will search for your questions and answer them
Thanks
san
Fri, 05/03/2013 - 11:22
Permalink
I observed that from below
I observed that from below questions, answers are not available. Please provide the key as to verify whether my answers correct or not
1)In define scope process project documents are updated which includes all except:
A. Stakeholder register
B. Requirement documentations
C. Requirement traceability matrix
D. Risk register
Ans could be D
2)What is non- work schedule activity?
A. It is effort hours available in Resource calendar which are not be utilized during a schedule.
B. It is buffer available in Critical Chain method
C. It is a type of activity, which runs parallel to the main activities, and not measured separately.
D. These are activities required efforts but no separate schedule.
Ans :B
3)While reviewing a schedule network and resource allocation of a sub-project, a senior manager, objects that in certain activities resources are over-allocated. Here Over allocation means:
A. One resource is allocated over 2 or more activities in same time.
B. More resources than required are allocated at certain activities in same time.
C. Few resources are idle in certain activities
D. All above
Ans:A
4)Schedule data for project schedule includes:
A. Mile stones, Schedule Activities, activity attributes, Activity related Assumptions and Constraints
B. Cash flow program, delivery and order schedules
C. Resource Histograms
D. All above
And :D
5)A project having BAC = 20000, in a point of time when its 80% work was over, its TCPI is reported as 1.2. What is its CPI?
A. 0.833
B. 1.20
C. 0.96
D. 0.90
Ans :C
Thanks
sspawar
Fri, 05/03/2013 - 15:13
Permalink
YES ALL 100 % TRUE
YES ALL 100 % TRUE