EAC formula-- AC+(BAC-EV)
Submitted by abdsal on Thu, 05/02/2013 - 05:54
Dear all,
Can you please explain the definition for the EAC formula:
"When the current cost performance is atypical for future project work and the future cost performace is expected to be in line with the original estimate"
Forums:


ostralek
Thu, 05/02/2013 - 11:46
Permalink
Abdsal, You can access all
Abdsal,
You can access all the PMP forumlas at Mister Exam (url = http://www.misterexam.com/pmp/pmp-formula)
Let me make it easy for you and all. In the exam it will be mentioned accordingly and you have to pick the clue and use the appropriate formula.
Estimate At Completion (EAC)
EAC=AC+(BAC-EV)
(CPI*SPI)
Used when both Cost & Schedule performance are considered.
Estimate At Completion (EAC)
EAC=AC+BAC-EV
If project is A-Typical, Whatever has happened, Project will be on Budget.
Estimate At Completion (EAC)
EAC=AC+ETC
In case of Re-baseling
Estimate At Completion (EAC)
EAC=BAC
SPI
If Schedule Variance continues
Estimate At Completion (EAC)
EAC=BAC
CPI
If Cost Variance continues
pmpnewster
Thu, 05/02/2013 - 15:03
Permalink
In the first EAC formula,
In the first EAC formula, you seem to have inadvertently included AC in the numerator. AC should be a separate term and not in the numerator.
Regards.
ostralek
Fri, 05/03/2013 - 07:55
Permalink
Thanks for pointing that
Thanks for pointing that out, PMPNewster!
abdsal
Fri, 05/03/2013 - 07:41
Permalink
dear ostralek thanks!!!
dear ostralek
thanks!!!