Distribute Information
Submitted by crushPMP on Thu, 04/25/2013 - 03:48
Which of the following are NOT considered a method in the Distribute Information process?
A. Speaking, Writing, Listening
B. Email, Fax, VoiceMail, Telephone
C. Project Meetings
D. Project Management Software
Forums:


Jgrind07
Thu, 04/25/2013 - 04:33
Permalink
Option A
Option A
crushPMP
Thu, 04/25/2013 - 14:12
Permalink
^ Correct
^ Correct. I went with Project Management Software as NOT considered a method in the Distribute Information process. No idea why D is not the correct answer!
BK
Thu, 04/25/2013 - 14:20
Permalink
I guess because Listening
I guess because Listening cannot be information distribution.
Jgrind07
Thu, 04/25/2013 - 17:14
Permalink
Look at section 10.3.2 in
Look at section 10.3.2 in PMBOK 4 and you will understand why D is a wrong option