Risk question - from Lehmann
Submitted by Geethika on Sun, 04/21/2013 - 09:07
Oliver Lehmann Question
Being the project manager in a high-risk electronics project with a lot of new
technologies, you developed a risk management plan and identified risks which
you documented in a risk register. Then, the risks were analyzed and response
planned.
It is getting obvious during risk monitoring and control meetings that the
documents you created are not very helpful. What have you probably done
wrong?
A You failed to use an RBS.
B You did the first processes alone.
C You did not identify Triggers.
D You did not calculate EMVs.
Answer is given as B, Can someone help justify or which is the correct answer?
Forums:


BK
Sun, 04/21/2013 - 10:16
Permalink
In my opinion:the document
In my opinion:
the document like risk register should be created with the help of project team, not only by PM.
Geethika
Sun, 04/21/2013 - 10:23
Permalink
yeah..
that's right..thanks!
cnpatilpmp2012 (not verified)
Sun, 04/21/2013 - 17:30
Permalink
answer is B ONLY
It's project team work and necessary stakeholders can be iutilized as expert judgment. On the contrary if you look at the options the elimination theory would filter it down to option B only as other options touch upon diferent risk planning processes / tools/ techniques but a single technique wouldn't have caused an issue unless the quetsion is referring to a particular risk management process out of control..
regards
CN Patil