technical work completed - confusing
Hi,
All technical work is completed on the project. Which of the following remains to be done?
a. verify scope
b. plan risk responses
c. create a staffing management plan
d. complete lesson learned
answer given is d. In my opinion it is confusing. I answered a.: is it not that after the technical work is completed it needs to be verified?
Explanation is: Did you pick Verify Scope? Then you may have forgotten that the Verify Scope process is done during project monitoring and controlling, not project closing
But why we have to jump directly to project closing after technical work is completed? If technical work is completed, then the deliverables are produced and needs to be verified before, is this correct?
Thanks


Geethika
Wed, 04/10/2013 - 20:35
Permalink
I think D only correct
If we refer Pmbok,pg 105, it is saying
Collect requirements:- Product requirements can be technical, security, performance etc
When all technical work is completed, it implies product is completed and we are into closing group..
So lessons learned is remaining to be done
This thread may also be of some use..
http://pmzilla.com/product-verification-question
al.zo
Wed, 04/10/2013 - 20:52
Permalink
Hi Geethika, Yes I agree, we
Hi Geethika,
Yes I agree, we are talking about a product here because of technical requirements.
Thanks a lot.