Bar Chart vs Milestone Chart
Hi Admin,
I have answered below question from PMZILLA (tough questions) and looking for your clarification.
Q. You have completed the schedule development of your project. You have bar charts and network diagrams finalized. In what situation will you use bar charts over network diagrams?
A.To verify the start and end dates of activity
B.To find dependency lines between activities
C.To make presentation to management
D.To determine the critical path
Correct Ans: C
But i have seen in Rita's book as Bar chart is report to the TEAM, and Milestone CHart is to report Management.


Julbrown31
Wed, 04/03/2013 - 02:42
Permalink
You're correct
I agree - it should be Team based on my understanding. Hopefully someone can clarify if our interpretation is incorrect.
admin
Fri, 04/05/2013 - 02:02
Permalink
C is the best answer from the
C is the best answer from the 4 choices given, not to say Bar charts cannot be used for other things. Of course it will have multiple uses.
motivation
Mon, 04/08/2013 - 02:58
Permalink
PMBOK will prevail
If you read PMBOK line by line, it says, bar charts are used to make presentation to management.
RITA may say whatsoever (not disparaging the book and content), however PMBOK will prevail when it comes to such contradiction.
Just go with C.
sspawar
Mon, 04/08/2013 - 11:31
Permalink
see last 2-3 replyies on
see last 2-3 replies on this thread
http://pmzilla.com/couple-questions-float
sandeepdel
Mon, 04/08/2013 - 23:38
Permalink
Look for best choice
Hi..pls look for best possible choice. Any single tool can be used for multiple things. So here will go for C.