cost management - percentage cost variance
Submitted by vijayavadrevu on Fri, 03/29/2013 - 11:54
WBS element Q is ------- budget by ----------- percent
WBS element |
PV |
EV |
AC |
P |
$1000 |
$1100 |
$1150 |
Q |
$2000 |
$1800 |
$2100 |
R |
$1000 |
$1200 |
$1050 |
S |
$2000 |
$1900 |
$1800 |
Ans is given as over budget by 16.67%
CV = EV-AC = 1800-2100 = -300
Hence over budget
% cost variance is (-300/2100)*100 = 14.28%. But the answer is given as 16.6%
Please confirm % cost variance formula
Forums:


sspawar
Fri, 03/29/2013 - 13:42
Permalink
(-300/1800)*100 = 16.6%EV
(-300/1800)*100 = 16.6%
EV is base(reference) value
AC is variable
Renji2013
Fri, 03/29/2013 - 13:43
Permalink
Think logically
Hi this could be done like this ..
As you said, we need to calculate the % cost variance. Now, think, what should it be based on ? As you saw there is an over budget issue here.. over.. with respect to which value ?
Here we got 1800 back by investing 2100. in otherways, for getting 1800 value we actually spent 2100. So the reference value to use is 1800.
-300/1800 * 100 = 16.6 %
Renji