cost management -- schedule variance -- percentage

 Using the table below, a comparison of the schedule variance of august as compared to July shows that the magnitude ($ value) of the variance has --------------- and the percentage change has  ---------------



Month


PV


EV


AC


June


$34,000


$34,000


$33,000


July


$18,000


$16,000


$20,000


August


$58,000


$60,000


$66,000

Ans is

 Improved, Improved

SV = EV-PV

SV in July = 16000-18000 = -2000

SV in August = 60000-58000 = +2000

SV has improved. How to conclude about % change??

 

 Pls use (ev-pv)/pv * 100 i.e variance from planned value.  In this question thinks are easy to compare as one sv is negative so in August all got improved. But for % change pls use the formula as it might be needed for another questions where finding will be not so easy. 

 Thank You !!!!

 with this formula of %age

in case of july, it is (-)0.11%

in case of augst , it is (+) 0.03%, hence% improved.

here in both questions concept is that, EV-PV should be better (more) than past month.

Thank You Sir

 


To do this mathematically u  need 2 values . the  earned value and planned value


% change is =  [new value - old value ] / [ old value ].x 100. PV value should be taken for division  because this is what you are comparing against. This can be used for any other calc.


Considering the changes as below ..simplified... 


july    EV =  2  PV =  4 ,


%change = 2 - 4/4  x 100  = - 100%


august  EV = 4 PV = 2 ,


%change =  4 -2 / 2 = +100%


Hence it is IMPROVED.


cheers


Renji

 Thank You Renji