cost management -- new duration
Submitted by vijayavadrevu on Fri, 03/29/2013 - 03:37
Using the data shown below, the new duration of the project is:
PV = $4,000, EV = $ 6,000, AC = $8,000, BAC = $12,000, Critical path = 15 weeks
Answer is given as 10 weeks
Can someone explain the concept?
Forums:


admin
Fri, 03/29/2013 - 06:13
Permalink
Since EV > PV by 50%, the
Since EV > PV by 50%, the project is ahead of Schedule and hence it will complete sooner , if you do the math, instead of 15 weeks, it will now complete in 10 weeks.
Renji2013
Fri, 03/29/2013 - 06:28
Permalink
Mathematically
If you want to go mathematically, it is
New Duration = Planned Duration / SPI = 15 /(6/4) = 10 weeks
cheers
sspawar
Fri, 03/29/2013 - 08:04
Permalink
It is good qn SPI =
It is good qn
SPI = 6000/4000 =1.5
BAC DURATION = 15 weeks
corresponding EAC DURATION = 15/1.5 = 10
vijayavadrevu
Fri, 03/29/2013 - 09:09
Permalink
Thank You Admin, Renji and
Thank You Admin, Renji and Pawar Sir