question on sequencing
Submitted by sajays on Mon, 03/25/2013 - 01:23
Can someone please confirm the below path?
Get formal acceptance
write lessons learned
release the team
close the contract
close project
QUESTION: Where will the conduct procurement audit fits into this. Is it after 'close the contract', then how will it make through the lessons learnt


sunitaPMP
Mon, 03/25/2013 - 02:04
Permalink
lessons learnt takes place
lessons learnt takes place through out the project ,its not in just while closing contract or project.Procurement audit happens while closing the contract,its part of close contract .
bpatel
Mon, 03/25/2013 - 02:17
Permalink
In one of Scordo Tests i
In one of Scordo Tests i attempted, Answer to one of the questions was that 'It is ok if Lessons learned are not documented throughout the project'
Also Deliverables are accepted in both Verify Scope(M&C) and Close Project, both are answers in many tests, sometimes both are choices
I am very confused which one to choose in exam to get it correct
Experts, please help
sunitaPMP
Mon, 03/25/2013 - 03:09
Permalink
yes you are right.But its
yes you are right.But its advisable to do the lesson learnt through out the project .if you do not have time to do that through out teh project life cycle ,then you must do the lesson learnt at the close project process
greenox
Mon, 03/25/2013 - 02:49
Permalink
The Project Team does LL
Typically you need the Project Team to conduct a Lessons Learned, you shouldn't release them before that. On the other hand, Contracts can take weeks, even months to close out, many times because of errors in verbiage, clarifications needed, etc.. that are not related to project perfromance but rather administration errors. It doesn't seem feasible to keep the Project Team tied up for that.
admin
Mon, 03/25/2013 - 04:10
Permalink
Search PMZilla for "Closing
Search PMZilla for "Closing Activities" or closing squence and you will find the relevant posts, read and I am sure your doubts will be clarified.