Time Management Questions- Please clarify with explanation

 

 

 

2)

 

 In both qns correct option is D

in 1st q  ---- middle one is critical and up G u cant expedite, hence H and j can be .

in second q --- critical path is c e f, and e f is common for other non critical hence take C.

Pawar Sir,

 

In second question ,  CEH will become critical path. I am considering activity H as it has long duration of 9 days. Please clarify.

For the first question the answer given was B (Move more resources to activity B)

and the explanation is as below:

"You need to select an activity on the path with activity G. This will allow activity G to start and finish earlier, meeting the milestone"

 

I am not clear with the explanation

I am inclined to agree with the answers you have marked on screen:

#1 B.  Because it seems that the imposed deadline has to be met... the question says 'meet that milestone'. So activity B should be crashed.  Not sure if activities H and J can be fast tracked esp if it's an FS relnship between these two.

#2 C.  Activity H because C-E-H seems to be the critical path. Either C or H can be shortened but H has greater scope of compression, so H.

Please post the official responses.

Thanks.

 

 

 option B and D will shorten the project length but only option B can help in meeting milestone.

option A and C will not help as these activity is not on critical path as of now.

 Q1-  is telling that activity G is constrained by an outside delivary, if you add additional source to B , G can not completed earlier, because of outside delivary constraint.

hence H and J is right answer. option D

Q 2 - Option C is correct - because option D - activity C  can not move it further, because activity E is depend on activity B also. there will be no impact on  shortening C . Hence H will be shorten.