When do we have to consider Project Manager to determine Number of Communication Channels
Submitted by bpatel on Tue, 03/19/2013 - 22:11
Working through some mockup tests, i have observed that in certain cases, you simply use n(n-1)/2 formula if 9 people are given and get the right result. Whereas in certain cases, the correct answer is add Project manager, so 9 becomes 10 and then use the formula
When to add PM, when not to add PM?
Forums:


sandeepdel
Tue, 03/19/2013 - 22:57
Permalink
Careful on question wording
We need to understand the question to come up for the value of n. for example if I say in a van there are 4 people and want to get the channels then ..n here is 4. But if we ask there are 6 passenger and 1 driver ...then my n will be 7 here. So we need to understand the question.. Hope this will help.
bpatel
Wed, 03/20/2013 - 19:25
Permalink
In the questions, they are
In the questions, they are writing
There are 5 team members
Or
7 Stakeholders
Does Pm count in this case or we have to add the PM.
sandeepdel
Wed, 03/20/2013 - 23:42
Permalink
Exam question
Hi in my exam I did not got any confusion question like this.. they were clear. For example you are five members and 2 new joins... So this time n=7. So all depends on question. If you have a complete question pls post and then let struggle with that question to get the answer.