Project Closure

Which of the following is true about project closure:
A) Contract closure is for each contract
B) Contract closure includes product verification and administrative closure
C) Administrative closure happens to close the project or each phrase
D) All of the above

..

Bingo,
But why Contract closure includes administrative closure is correct?

admin's picture

No where does it say that contract closure include admin closure ?...

all of the above include "B"
B) Contract closure includes product verification and administrative closure

 Does contract closure includes administrative closure ?

 

Administrative closue will happen at the close phase. whereas close contract can happen even before that ? Am I right ?

 P 341 CLOSE PROCUREMENT

clears every thing

salient points are:

  1. a contract may a be phase
  2. finalization of claims is a administrative closing activity of close procurement or contract
  3. thus administrative closure is an itrative activity, which exists before of close procurement or contract and after close procurement or contract for close of projects or phase.

 

I also support for the answer d

question being asked is project closure:

In a project, there will be lot of contracts which needs to be closed and it has been adhered but however this contract is one of the subset of project closure

With regard to anser b & C, contract closure includes prodct verification and administrative closure, see PMBOK 4.6(Page 99/100)

Since all the three are related to project closure activities and hence answer should be D

 

 

I saw a question on which one comes first Contract closure or Administrative closure. For which I found contract closure. If contract closure has administrative closure in it, how come administrative closure will be last ? Do we need to scan the question whether it is asking that project level ?