Contract - Risk Mitigate or Transfer response strategy?
Submitted by Geethika on Tue, 03/19/2013 - 09:38
Can someone please tell whether Contracts are Risk Mitigate or Transfer response strategy? Which is best option when both are given? Is it dependent upon specific type of contracts?
In some places, I see its Mitigate strategy.
But in Pmbok (Pg 303), Contracts can be used to transfer liability of some risk to seller. Cost-plus contracts may transfer cost risk to the buyer. And FP contracts may transfer cost risk to the seller.
Thanks.
Forums:


sspawar
Tue, 03/19/2013 - 12:40
Permalink
can you append those
can you append those examples here.
Geethika
Tue, 03/19/2013 - 13:52
Permalink
Sir,I have read this in
Sir,
I have read this in brainbok, which also seems to be a renowned site recommended by our fellow pmp's
If an Organization decides to use a contract in order to reduce a project risk, what kind of risk response strategy are they using? MITIGATE
So got confused on this..
Thanks.
sspawar
Tue, 03/19/2013 - 14:04
Permalink
thats why I asked the real
thats why I asked the real (word to word) , question.
here key word is to reduce the risk , hence answer will be mitigate.
Geethika
Tue, 03/19/2013 - 14:43
Permalink
Thanks Sir, Really great and
Thanks Sir, Really great and kind of you!!
Can I assume in this case it is Mitigate, otherwise generally contracts are to be used to Transfer risks?
sspawar
Wed, 03/20/2013 - 04:09
Permalink
It depends on core subject
Generally contracts are to be used toTransfer risks --- it is true
But correct option may depend on core subject of question.
sangc (not verified)
Sun, 04/07/2013 - 22:29
Permalink
Won't transfer risk reduce
Won't you reducing the risk when you "transfer risk"?
sspawar
Mon, 04/08/2013 - 00:28
Permalink
Eollow PMBOK sense.
Follow PMBOK sense.
sandeepdel
Tue, 04/09/2013 - 00:02
Permalink
Contract ...???
It depends on perspective. For example, you have a project to design a car and during planning you found that QC for car safety can not be done by organization as lacks capability. So it's transfer. But if you put a contract to get infrastructure and train you resources..then it's mitigation.
So if risk response plan still stays with project then it's mitigation otherwise transfer.
mitigation - probability or impact is reduced
transfer - risk for which you don't care any much :)