PMstudy free mock question query
Submitted by amber on Wed, 02/20/2013 - 18:55
For below qyestion on what basis it is assumed that EAC formula qiven in solution will be applied as question does not states that current variances are typical. Please advise.
| You are working on a 12 month assignment to build a website with 4000 pages for $ 1,000,000. You are supposed to spend $ 250,000 every 3 months. After 6 months, you determine that only $ 400,000 of work is completed and cost incurred is $ 800,000. What is the ETC? |
||
| Choice 1 | $ 2,000,000 | |
| Choice 2 | $ 1,500,000 | |
| Choice 3 | $ 1,000,000 | |
| Choice 4 | 1,200,000 | |
| Correct Choice : 4 | ||
| Justification : |
||
| The default value of EAC (assuming current variances are typical) is calculated as below: EAC= AC + (BAC-EV)/CPI = $800,000 + ($ 1,000,000 - $ 400,000)/($ 400,000 / $ 800,000) = $ 800,000 + ($ 600,000/0.5) = $ 2,000,000 So, ETC = EAC – AC = $ 2,000,000 - $ 800,000 = $ 1,200,000 |
||
Forums:


sgadewar
Fri, 02/22/2013 - 17:59
Permalink
PMP Q
Wow this is a PMP Q
AP
Fri, 02/22/2013 - 18:12
Permalink
Formula confirmation
Hi All,
I came across a page in Deep Fried Brain (http://www.deepfriedbrainproject.com/2010/01/solving-estimate-at-completion-puzzle.html).
It says that the formula (for typical variances) EAC = AC+((BAC-EV)/CPI) was from third edition of PMBOK and the current edition has simplified the same formula to EAC = BAC/CPI.
Aplpying the latest formula for the above question,
EAC = 10,00,000/(4,00,000/8,00,000) = 20,00,000
ETC = EAC - AC = 20,00,000-8,00,000 = 12,00,000 - Same answer as above.
Hence I believe that we can use the simplified formula (EAC = BAC/CPI) for typical variances in the exam. Please correct me if I'm wrong.
Regards,
Arun.