Activity Duration Formulae CheatSheet Anil Tanguturi
Submitted by y0zh on Thu, 02/21/2013 - 09:52
I'm checking Formulae CheatSheet Anil Tanguturi and found that
6 | Activity Duration | (EF – ES) or (LF – LS) |
7 | Forward Pass: (Add 1 day to Early Start) | EF = (ES + Duration - 1) |
8 | Backward Pass: (Minus 1 day to Late Finish) | LS = (LF - Duration + 1) |
My question, is Activity Duration correct, based on that +1 was considered for EF and LS?
Forums:


sspawar
Fri, 02/22/2013 - 03:56
Permalink
In case 6 -- formula is based
In case 6 -- formula is based on 0 start method
In case 7 and 8 - formula is based on 1 start method.
See my blog
er-sspawar.blogspot.in
there is an example given on 0and 1 start method, observing that you can understand.
can you forward me this cheat sheet complete at pawarindo@gmail.com
y0zh
Fri, 02/22/2013 - 12:27
Permalink
Thanks sspawar, that's why I
Thanks sspawar, that's why I was asking to ensure
Here is the link:
http://pmzilla.com/files/00_PMP_Formulae_CheatSheet_Anil_Tanguturi.pdf