Total Float and Float in Network Diagram
Submitted by jjrr007 on Mon, 12/01/2008 - 00:06
I wanted to please ask how can I calculate total float when given a portion of a network diagram.
For a particular example, please feel refer to question 18, in the Oliver Lehmann practice test at:
http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm
Thanks!
Forums:


msachin
Tue, 12/30/2008 - 19:13
Permalink
Eliminating the wrong
Eliminating the wrong choices.
Adil
Mon, 01/05/2009 - 12:06
Permalink
Total float
Float =LS-ES=LF-EF
in the example of question 18:
ES=day 16 EF=Day 21 (forward)
LS=day 26, LF=day 31 (backward)
so the float of activity B is 10.
the question is: is-it total float or free float?
I think it's important to look at the question: start dates are early morning and finish dates are evening this important information involves that 10 is total float, because if the free float is 10: if activity B is delayed 10 days it will finish on day 31 evening; early start of activity C will be delayed! which is oposit to the definition of free float.
I hope I'm correct please see the definition of free float.
happyinlove505
Wed, 02/20/2013 - 12:13
Permalink
I think that your
I think that your explanation is correct and thank you for that :)
Initially, I did not notice this point about early mornings and selected free float. Now I see what was wrong :)
vkajith
Wed, 12/31/2008 - 10:51
Permalink
2 Correct Answers?
I have an inkling that 2 answers are coreect.
The activity B has a free float as well as total float of 10 days.
Even though a portion of the network diagram is only shown there, we can safely assume about the total float because the subsequent activity falls on the critical path.
Please correct me if I am wrong
Best Regards
Ajith
happyinlove505
Wed, 02/20/2013 - 12:41
Permalink
I think you are wrong in
I think you are wrong in saying that subsequent activity falls onto a critical path.
Look attentively, subsequent activity has a float of 1 which means it is not on critical path.
umanath
Fri, 02/20/2009 - 04:46
Permalink
Total Float and Project Float
I think that both A and B are correct in this OliverLehmann's example because:
Free Float = LS - ES or LF - EF = 10d
Total Float = LF - ES - D( duration of activity) = 10d
- Umanath
HN-LB
Mon, 03/02/2009 - 10:34
Permalink
Total Float & Free Float
Hi All,
I have question for you:
If you have two resources, one working on an activity & having free float of 4 & another one working on another activity and having total float of 8, which resource you use to crash a critical path activity?
Awaiting your kind answers,
Regards,
NH
deepfriedbrain
Fri, 11/13/2009 - 17:13
Permalink
Total Float vs Free Float
You can review the following article for a simple explanation of this topic:
Total Float vs Free Float