Hi Kindly explain 31 question from Oliver 75 online question
pkukilla
Thu, 08/19/2010 - 03:32
Permalink
ES of Activity1 =1 EF of Activity1 =20
ES of Activity 2 =21 EF of Activity2 =30
EF of Activity3 =28 ( Since Activity2 and Activity3 are having FF-2 relationship i.e Activity3 will finish 2 days before Activity2 finishes)
ES of Activity4 =32 as there is 3 days lag after Activity3
EF of Activity4 = 37
pkukilla
Thu, 08/19/2010 - 03:32
Permalink
ES of Activity1 =1 EF of
ES of Activity1 =1 EF of Activity1 =20
ES of Activity 2 =21 EF of Activity2 =30
EF of Activity3 =28 ( Since Activity2 and Activity3 are having FF-2 relationship i.e Activity3 will finish 2 days before Activity2 finishes)
ES of Activity4 =32 as there is 3 days lag after Activity3
EF of Activity4 = 37