Oliver 175 Q Set ( Please explain Q : 94:
Submitted by sai_murthy on Wed, 08/18/2010 - 03:34
The duration uncertainity - defined as pessimistic minus optimistic estimate - of the first activity is 18 days and the second estimate has uncertainity of 24 days . Applying PERT formula fo rpaths , what is the duration uncertainity of the entire path
a. 21 d
b. 30 d
c. 42 d
d. No statement is possible
Forums:


pkukilla
Wed, 08/18/2010 - 18:37
Permalink
This is explained in one of
This is explained in one of the forums. Here is the link
http://forums.oreilly.com/index.php?showtopic=2978&pid=35948&mode=threaded&start=#entry35948
sai_murthy
Thu, 08/19/2010 - 01:04
Permalink
Excellent. Thank You very
Excellent. Thank You very much.
pkukilla
Wed, 08/18/2010 - 18:45
Permalink
This is explained in one of
This is explained in one of the forums. Here is the link
http://forums.oreilly.com/index.php?showtopic=2978&pid=35948&mode=threaded&start=#entry35948