What is the EAC for the project
Activity A is worth $800, is 100% complete, and actually cost $800. Activity B is worth $300, is 90% complete, and actually cost $480 so far. Activity C is worth $800, is 75% complete, and has cost $700 so far. The total budget is $4,000. What is the estimate at completion for the project?
A. $4,761.91
B. $4,742.52
C. $4,742.54
D. $4,705.88
Here the question did not specify whether there is variance from BAC (EAC=BAC/CPI) or whether the variance are either typical(EAC= AC + [ (BAC - EV) / CPI*SPI ] or atypical of the future (in which sace EAC = AC + (BAC -EV) .
How do we know which EAC formular to use?


daso
Sun, 02/10/2013 - 13:09
Permalink
B. $4,742.52
B is correct.
Just sum up AC and EV and calculate CPI. Then use EAC = BAC/CPI and you got it. Since there is nothing stated about the future expectations the current variance will be used for the future... -> BAC/CPI
sspawar
Sun, 02/10/2013 - 15:03
Permalink
IN THE SAME WAY AS EARLIER
IN THE SAME WAY AS EARLIER POST
HERE NO ONE ANSWER WILL MACH.
ANS WOULD BE = 4366.67
daso
Sun, 02/10/2013 - 15:15
Permalink
why that? how do you
why that? how do you calculate?
sspawar
Sun, 02/10/2013 - 15:47
Permalink
if total AC = 800+480+700 =
if total AC = 800+480+700 = 1980
against EV = 800+270+600 = 1670
CPI = 1670/1980 = .843434
EAC = 4000/0.843434 = 4742.52
thus OPTION B , may be answer
but I was following PMBOK pattern of table 10-15, working out individual (as calculated in eralier example)