ETC Question, please help me to solve it
Submitted by raza82 on Sat, 02/02/2013 - 11:40
You are working on a 12 month assignment to build a website with 4000 pages for $ 1,000,000. You are supposed to spend $ 250,000 every 3 months. After 6 months, you determine that only $ 400,000 of work is completed and cost incurred is $ 800,000. What is the ETC?
Choice 1 $ 2,000,000
Choice 2 $ 1,500,000
Choice 3 $ 1,000,000
Choice 4 1,200,000
Forums:


sspawar
Sat, 02/02/2013 - 15:36
Permalink
very good question
very good question RAZA...
CPI = 0.5
SPI = 0.8
YOUR PROJECT IS TIME (SCHEDULED DATE) CONSTRAINED
HENCE ETC = 600000/ (0.5*0.8) = 1500000 (OPTION 2)
raza82
Sat, 02/02/2013 - 17:06
Permalink
Well thats the not the answer.....
Well thats the not the answer given by the simulator...........
sunitaPMP
Sat, 02/02/2013 - 16:44
Permalink
I think Ans is D)
I think Ans is D)
raza82
Sat, 02/02/2013 - 17:06
Permalink
Please elaborate
Can u explain why plz?
sunitaPMP
Sat, 02/02/2013 - 17:44
Permalink
CPI=1/2BAC=1000,000EAC=BAC/CP
CPI=1/2
BAC=1000,000
EAC=BAC/CPI=2000,000
ETC=EAC-AC=2000,000-8000,000=1200-option D
what is teh correct ans?
steelproject2012
Sat, 02/02/2013 - 17:58
Permalink
I thought this formula is
I thought this formula is used when there ARE NO VARIANCES
But variances do exist for CV(EV - AC = -400) and SV (EV - PV = -100), right?
sunitaPMP
Sat, 02/02/2013 - 18:05
Permalink
my thinking on this,this is
my thinking on this,
this is fundamentally flawed .In this case we calculate EAC as
EAC=AC+ETC
To calculate EAC i used BAC/CPI
raza82
Sat, 02/02/2013 - 18:35
Permalink
Your calculation....
Your calculation gives the answer -6000000, not 1200000.
sunitaPMP
Sat, 02/02/2013 - 18:41
Permalink
ETC=EAC-AC=2000,000-800,000=1
ETC=EAC-AC=2000,000-800,000=1200,000
sunitaPMP
Sat, 02/02/2013 - 18:55
Permalink
deleted
corerction
2,000,000-800,000=1200,000
Is this corerct now?I made mistake in putting 0s.
Let em know what is teh correct ans
steelproject2012
Sat, 02/02/2013 - 17:55
Permalink
EV=$400k; PV=$500k, AC=$800k;
EV=$400k; PV=$500k, AC=$800k; BAC=$1M;
th9063
Sat, 02/02/2013 - 19:06
Permalink
Option
Option 4
EAC=AC+BAC-EV/CPI
CPI=EV/AC
400,000/800,000
=.5
EV=400,000
AC=800,000
BAC=1,000,000
EAC=AC+BAC-EV/CPI
=800,000+(1,000,000-400,000)/.5
=2000000
ETC=EAC-AC
2000000-800000
=1200000
steelproject2012
Sun, 02/03/2013 - 03:48
Permalink
Corrected typo:(i) EAC = AC +
Corrected typo:
Why is no one giving consideration to the constraints b4 applying the formula even though the 3 formulae give different answers.
sspawar
Sun, 02/03/2013 - 04:43
Permalink
Your query ii) --- , in
Your query
ii) --- ,
in options --- atypical , choice is not given. (as the option may be for = 600000) , hence this formula will not be applicable.
second when in question time constraint is given -- that in 12 month you have to complete this project.
it is must to consider SPI while forecosting ETC , along with CPI (your query iii - this formula will not be applicable).
once you can leave CPI, but cant leave SPI, because , time constraint is given but typical / atypical trend in terms of CPI/ CV is not given.
but in that case answer would be - 600000/ SPI(0.80) = 750000, and this option is not given.
Hence only option 2 = 600000/0.80*0.50 = 1500000, will be the right choice.( your option i -- this is only possible option here)
read p 185 1st para:
EAC forecast for ETC work considering both SPI and CPI factors. In this forecast, the ETC work will be performed at an efficiency rate that considers both the cost and schedule performance indices. It assumes both a negative cost performance to date, and a requirement to meet a firm schedule commitment by the project. This method is most useful when the project schedule is a factor impacting the ETC effort. Variations of this method weigh the CPI and SPI at different values (e.g., 80/20, 50/50, or some other ratio) according to the project manager's judgment. Equation: AC + [(BAC — EV) / (cumulative CPI x cumulative SPI)].
sspawar
Sun, 02/03/2013 - 03:02
Permalink
From where you got this
From where you got this question, Only choice 2 is right answer.
raza82
Sun, 02/03/2013 - 05:23
Permalink
PM Study free mock
Answer given is 1200000
sunitaPMP
Sun, 02/03/2013 - 05:11
Permalink
Hi raza82,Can we have the
Hi raza82,
Can we have the correct answer with explanation given in simulator?
Thanks..
raza82
Sun, 02/03/2013 - 05:22
Permalink
According to the simulator
Answer is 1200000. I dont understand why they have used this formula for caclulating EAC, th9063 and sunita got it right according to simulator, can someone explain please.
The default value of EAC (assuming current variances are typical) is calculated as below:
EAC = AC + (BAC-EV)/CPI
EAC = $800,000 + ($ 1,000,000 - $ 400,000)/($ 400,000 / $ 800,000)
EAC = $ 800,000 + ($ 600,000/0.5)
EAC = $ 2,000,000
raza82
Sun, 02/03/2013 - 05:26
Permalink
I think
I read somewhere that
EAC = AC + (BAC-EV)/CPI is same as EAC = BAC/CPI
sspawar
Sun, 02/03/2013 - 06:05
Permalink
Yes it is true, in case of
Yes it is true, in case of typical case.
bks CPI = EV/AC is calculted on basis AC wrt its EV. and thus AC = EV/CPI
Now
EAC = AC + (BAC-EV)/CPI
replace AC
EAC = EV/CPI + (BAC-EV)/CPI = BAC/CPI
but in case of
CPI and SPI combined this formula will not work , because EV of CPI is different than EV of SPI.
in below example:
for CPI , AC = 800000 against EV = 400000, and for SPI, (PV) = 500000 against EV =400000
raza82
Sun, 02/03/2013 - 06:23
Permalink
Incase
Incase of typical variance i dont think we need to use this formula, EAC = AC + (BAC-EV)/CPI
We can just go ahead and use EAC = BAC/CPI.
Am I right?
sspawar
Sun, 02/03/2013 - 06:33
Permalink
Definitely
Definitely
rjbuzzing
Sun, 02/17/2013 - 13:17
Permalink
4 formulas of EAC ?
EAC = BAC / CPI (No Variances and current CPI will continue in future)
EAC = ETC + AC
EAC = AC + (BAC - EV)
EAC = AC + (BAC - EV) / CPI * SPI
How can we apply first formulae here, since i do see variance in past, how can we gaurantee that there will be no more in future based on the text of the question ?
raza82
Sun, 02/17/2013 - 16:14
Permalink
As I understand....
...from various books, fourms, notes.....that if nothing is given in the question, the most common formula for calculating EAC is EAC = BAC/CPI
Having said that...in this question there is no indication that this is a typical case or things are gonna improve or in future work will be peformed at the budgeted rate, so we assume that the current cost performance will continue in the future, hence EAC = BAC/CPI
Vanessa362
Mon, 09/02/2013 - 10:36
Permalink
ETC Question, please help me to solve it
ETC Question, please help me to solve it is something I was looking for , thanks a1-paris-apartments. For
contact us .