In Conduct Procurements, which plan is the INPUT :
a: Project Management Plan
b: Procurement Management Plan
Which one I need to select ::
As per PMBoK, Fig-12-4 the INPUT say as Project Management Plan, but if we see Fig 12-5, it says as "Procurement Management Plan
Forums:


jagjitdhaliwal@...
Sat, 08/14/2010 - 20:17
Permalink
Hi Sai, Both answers are
Hi Sai,
Both answers are correct as Procurement Mgmt Plan is part of Project Mgmt Plan only. In case, question mentions both answers, then it's better to select specific plan rather than general project mgmt plan.
Seniors may confirm my understanding.