IRR VS NPV
Submitted by Ahmad1111 on Sun, 01/27/2013 - 01:04
Just started checking out some pmp question, clicked the first link in the free pmp exam list, and I got baffled by this one:
Based on the information provided below, which project would you recommend for being pursued?
Project I, with BCR (Benefit Cost ratio) of 1:1.6;
Project II, with NPV of US $ 500,000;
Project III, with IRR (Internal rate of return) of 15%
Project IV, with opportunity cost of US $ 500,000.
Forums:


sspawar
Sun, 01/27/2013 - 06:21
Permalink
search old
search old posts
http://www.pmzilla.com/need-your-inputs-0
Ahmad1111
Mon, 01/28/2013 - 02:05
Permalink
Thanks for the link man.
Thanks for the link man. Unfortunately didn't come out with anything. People argued or both B and D.
admin
Mon, 01/28/2013 - 03:55
Permalink
The entire discussion is in
The entire discussion is in that thread and the rationale for correct answer is given by Rita. Its her question bank and some of the ambiguity maybe by design. Answer is B as othere options cannot be considered due to insufficient data
Ahmad1111
Mon, 01/28/2013 - 06:14
Permalink
Why is B the answer since, as
Why is B the answer since, as you said, there is insufficient data? Shouldn't D be the answer? D is pretty much saying that.. insufficient data.
To clarify my issue, let me rephrase the question: Why would you recommend project 3 when project 2 has the potential to be better?
sspawar
Mon, 01/28/2013 - 11:08
Permalink
Dont give importance to such
Dont give importance to such questions.