PMPforsure freetest 3rd question on Early state(networking diagram).Has anyone tried?
Submitted by sunitaPMP on Tue, 12/11/2012 - 22:34
Can anyone please explain the 3rd question of freetest from PMP4sure.This is a networking diagram question.
As far as i know Early start date of 1st activity would be 1 and not 0.Can anyone please help me with this question.Also please let em know why that is the correct answer.
Thanks
Forums:


mkar
Tue, 12/11/2012 - 23:41
Permalink
Zero or one no impact
Hi Sunita: I read from different sources that either you start your network diagram with one or zero, the answer will be the same. I solved problems with both and I got the same answers. My exam is on Dec 21st. I did not solve PMP forsure.
bonnettja@msn.com
Wed, 12/12/2012 - 02:29
Permalink
I had the same question...
According to the Rita book you start with 0, not 1. I have seen it all different ways from exam bank to exam bank. From what I read Ritas way is right. Let see what other reply.
bonnettja@msn.com
Wed, 12/12/2012 - 02:29
Permalink
I had the same question...
According to the Rita book you start with 0, not 1. I have seen it all different ways from exam bank to exam bank. From what I read Ritas way is right. Let see what other reply.
sspawar
Wed, 12/12/2012 - 05:11
Permalink
Write down your problem here
any mock test q does not appear in same order, they probably always suffle them. and who will go to take this much exercise.
Better narate your problem - here
sunitaPMP
Wed, 12/12/2012 - 05:21
Permalink
Its a network diagram.I dont
Its a network diagram.I dont think they are shuffling it.And am requesting those who are planning to take pmp4sure free test and see this question.
sspawar
Wed, 12/12/2012 - 11:45
Permalink
OK I have seen that test question
that question
and your
query
please see this link
http://www.pmzilla.com/time-management-question
and also
http://www.pmzilla.com/pmi-says-exam-start-0