Need Help for some questions
Submitted by Anonymous (not verified) on Tue, 12/04/2012 - 03:08
dears ,
can anyone help abou the right answer for the below ,
in the arrangement of the process what is done before what in the folowing two examples
( Release the Team ........Close the contract ) because some site says that and some says ( close the contract ( first ) then release the team .....) ???????
and also in ( verify Scope and Control scope ) what is before what done .......???
thanks
Forums:


aarush78
Tue, 12/04/2012 - 03:23
Permalink
Hi Hope you have PMI
Hi
Hope you have PMI membership...I also had the same doubt and then i came to know about this book on PMI site from Kim Heldman ..it has a dedicated last chapter on closure and you will find this chapter very useful..it very beautifully explains administrative closure , contract closure and procurement closure
http://pmi.books24x7.com/assetviewer.aspx?bookid=32020&chunkid=803159536
Also you can go through the following material available on PMI site
http://www.pmi.org/en/Certification/Project-Management-Professional-PMP/~/media/PDF/Certifications/PMP%20Examination%20Content%20Outline_2010.ashx
Just remember one thing releasing the team is not a formal official task . A PM would require team members inputs and help for closure activities and once completed then would release the team
Sacramanto (not verified)
Tue, 12/04/2012 - 03:37
Permalink
thanks
thanks for your care ,
sspawar
Wed, 12/05/2012 - 01:41
Permalink
very well explained by Arun
You can also refer this thread:
http://www.pmzilla.com/close-projectprocurement#comment-22053
tmanivannan
Wed, 12/05/2012 - 03:43
Permalink
As per Rita: 1. Close
As per Rita:
1. Close Procurement
Activities Perform Procurement Audit = > Reach Negotiated Settlement => Create Lessons Learnt => Complete Final Contract Perf. Reporting => Verify the Product => Issue formal Acceptance => Update records => Perform Financial Closure
This leads to Formal acceptance and Closed Procurements.
2. Then Close Project or Phase.
Confirm all work is done => (Procurement Closures) => Gain Final Acceptance of Product => Complete Financial Closure => Hand off completed Project => Get Feedback => Complete Final Perf. Reporting => Index and Archive Records => Update Lessons Learned.
Thanks
Mani.