Scope Related Question

Members,

Need help with this question from Rita's

During a meeting with some of the project stakeholders, the project manager is asked to add work to the project scope. The project manager had access to correspondence about the project before the project charter was signed and remembers that the project sponsor specifically denied funding for the scope mentioned by these stakeholders. The BEST thing for the project manager to do is to

A. Let the sponsor know of the stakeholder's request

B. Evaluate the impact of adding the scope

C. Tell the stakeholders the scope cannot be added

D. Add the work if there is time available in the project schedule

I marked answer as A which is incorrect.

My answer is B.  First we should analayzed the impact before making any decesion

Hello:-


 


The answer is "C" since it is already decided by the Sponsor that he is not funding for this particular Scope.


 


However, if the request was from the customer then option "B" would be a better choice amongst the four.


 


Thank You!!!


 


KK....

 The answer to this question is C.

there is no mention of customer making the request.

try and deal every question on its merit.

Regards,