Need help on the answers to the following :-

 1. In a project if the sponsor is replaced who will manage the budget ?

a  sponsor

b project manager

c financial controller

d stakeholders

 

2. There is a project , in which one of the room 's painting is completed at the rate of $100 per square foot . At the end of the project the data for the same has been saved . What do you think why this data would be used for in future ?

a  Estimate Budget

b Lessons learned 

admin's picture

1.. PM manages the budget, Sponsor is the one who approves budget and any ammendments to budget


2. Since its end of project it should be lessons learned or for future estimations