Configuration management -PL reply with explanation- scorers comments are welcomed
Submitted by sspawar on Wed, 07/25/2012 - 04:04
Configuration management is a process for applying technical and administrative direction and surveillance of the project implementation. Which activity is not included in configuration management?
A. Controlling changes to the project deliverables
B. Scope verification
C. Automatic change request approvals
D. Identification of the functional and physical attributes of the project deliverables
Forums:
Ramana_99
Wed, 07/25/2012 - 04:48
Permalink
D
D
krantikumar50
Wed, 07/25/2012 - 04:52
Permalink
Answer
Respected Pawarji Sir,
The answer is an obvious "D". What is that confusing you respected Pawarji Sir?
Warmly, KK....
aliweb
Wed, 07/25/2012 - 05:16
Permalink
I will go with option B.
I will go with option B.
sspawar
Wed, 07/25/2012 - 05:22
Permalink
I want to call all recent and old connected passouts
Please guide here
krantikumar50
Wed, 07/25/2012 - 05:26
Permalink
On Second Thoughts...
Respected Pawarji Sir,
On 2nd thoughts, I feel Scope Verification is the tight and right answer.
What does your answer sheet say?
Warmly, KK...
RaviDatt
Wed, 07/25/2012 - 05:31
Permalink
Option A is part of Change
Option A is part of Change Control System which part of CMS
Option B looks out of place to me here.
Option C is again part of Change Control System which is part of CMS. In case of emergency, we require auto approval and later a formal document can be submited for change process to kick start.
Option D looks like part of Configuration Control . CC deals with actual product specification. Product specification would be maintained by CC.
Looks like option B is answer here.
Let me know ?
hnsrinivas1
Wed, 07/25/2012 - 08:14
Permalink
Option C is correct
Option C is correct as it is not a part of Configuration managment.
hnsrinivas1
Wed, 07/25/2012 - 08:29
Permalink
Explanation for Option C
Hi all,
Scope verification is part of Configuration management. Detailed explanation regarding Configuration management can be found in attached links.
http://www.deepfriedbrainproject.com/2010/03/configuration-management-system-quick.html
http://www.deepfriedbrainproject.com/2010/05/activities-configuration-management.html
There is no process which is automated in regard to Change request approval.
sspawar
Wed, 07/25/2012 - 10:50
Permalink
Thank ! ShriNiwas
Automatic change contol is not any process/activity or plan in any KA or PG.
And thus C would be correct.
And its meaning is that scope is verified under configuration managementsystem
marcosanchez
Mon, 05/14/2018 - 08:55
Permalink
Do you have any new questions
Do you have any new questions? I see the correct answer is C.