Question on RWP
Submitted by Ramana_99 on Tue, 07/24/2012 - 06:05
- When would Rolling Wave Planning be useful in a project?
- You should use Rolling Wave Planning to help you achieve the appropriate level of detail in each work package at the right time.
- You should use Rolling Wave Planning to determine the correct sequencing for long term items.
- You should use Rolling Wave Planning to help you organize team member's activities within a large project group.
- You should use Rolling Wave Planning to help you determine which activities are more important and should be done first.
Regards,
Ramana
Forums:


sspawar
Tue, 07/24/2012 - 06:24
Permalink
A
A
krantikumar50
Tue, 07/24/2012 - 06:33
Permalink
Answer
Answer is "A"....
Ramana_99
Tue, 07/24/2012 - 06:45
Permalink
Correct
Yes, you both are correct.