One more question on PHRM...
Submitted by krantikumar50 on Sat, 07/21/2012 - 13:36
All,
A question on PHRM,
Q: You meet with the project sponsor, and the conversation covers the following topics: availability, competencies, experience, interest, and costs of the potential project team. The item referenced are part of which of the following?
A. Project resource Histogram
B. Resp Assignment Matrix
C. EEF
D. Org Breakdown Structure.
Warmly, KK....
Forums:


sspawar
Sat, 07/21/2012 - 15:00
Permalink
I go for B
because Resource Histogram could not keep interest metrix.
So only RAM , - have various type of grphical charts, like RACI. Text etc.
RaviDatt
Sat, 07/21/2012 - 15:45
Permalink
I will go with C.
I will go with C.
karthik21
Sat, 07/21/2012 - 18:24
Permalink
My option is "C" as well
My option is "C" as well
sspawar
Sat, 07/21/2012 - 23:40
Permalink
yes it is C
PMBOK p 227, aquire team input
krantikumar50
Sun, 07/22/2012 - 04:34
Permalink
Right answer is...
Respected Pawarji Sir,
Yesterday, when I saw you giving the wrong option, I did not want to say anything because I can do anything but even in the wildest imagination I can never say that respected Pawarji Sir is untrue. Now, that you say its "C", I give the right answer.
Yes, the true option is indeed "C".
Warmly, KK...